Paraseal Details

Back Filled Walls

Paraseal installation/seams running vertically
Paraseal installation/seams running horizontally
Paraseal installation/close clearance at masonry wall
Tie-in between below floor Paraseal and wall Paraseal
Tie-in between wall Paraseal and horizontal deck Paraseal
Tie-in Paraseal to other existing waterproofing
Typical grade line termination
Typical grade line termination
Typical pipe penetration detail
Typical outside corner
Typical inside corner

Below Slab On Grade

Simple slap-system A
Mat slab-system B
Mat slab with protective slab-system C
Mat slab with mud slab-system D
Simple slab-system A
Mat slab-system B
Mat slab with protective slab-system C
Mat slab with mud slab-system D
Tie-in between backfilled wall/footing and floor slab
Tie-in between backfilled wall/footing and mat slab/protection slab
Tie-in between backfilled wall and mat slab/protection slab
Tie-in between backfilled wall and mat slab/mud slab
Tie-in between blindside wall/footing and floor
Tie-in between blindside wall and mat slab/protection slab
Tie-in between blindside wall and below floor waterproofing
Termination at floor to interior wall face. HDPE side down
Termination at floor to interior wall face. HDPE side up
Floor to wall expansion joint
Mid floor expansion joint
Thru floor penetration (cast-in-place)
Thru floor penetration (cast-in-place)
Thru floor penetration (blocked out and plugged)
Thru floor penetration
Concrete pile with pile cap
Concrete pile with mat slab
Footing at interior column
Typical fold detail at beow to wall inside corner
Blindside construction of elevator, sump, or other below floor pit

Blindside Walls

Paraseal LG installation over wood lagging with steel piles
Paraseal LG installation over steel sheet piling
Paraseal LG installation over augered caisson
Paraseal LG installation over shotcrete with concrete piles
Paraseal LG installation over a slurry wall
Paraseal LG installation over chemically stabilised earth
Interrupting Paraseal LG at vertical soldier piles - plan view
Installing Paraseal LG directly over steel soldier pile - plan view
Installing Paraseal LG over lagging board gaps - plan view
Paraseal LG installation over a slurry wall
Paraseal LG installation at studs or form tiles
Paraseal LG installation at tie-back
Paraseal LG installation at tie-back blockout method
Paraseal LG installation at horizontal blindside to backfilled transition
Closing off the top of infill material between lagging and wall
Typical temporary termination at top of earth retaining system
Paraseal LG installation at wall penetration
Blindside walls. Termination above grade
Below grade waterproofing. Termination at grade line
Paraseal LG installation at concrete pilaster - plan view
Expansion join - plan view
Paraseal LG installation at blindside to backfilled transition - plan view
Paraseal LG installation at wall to below floor tie-in (see Section C)
Proper installation of shotcrete against Paraseal LG
Termination at top of deck
Paraseal LG installation at jon in lagging walls - plan view
New wall to existing wall tie-in - plan view
Proper anchoring of Paraseal seams

© Copyright 2016 Equus Industries Ltd. All rights reserved.